-This will serve as an update for the next two day, 8/4 and 8/5. Union Construction Crews completed conduit installation along Uinta Dr. from Spruce Cir. to Bear Ln. Tomorrow, 8/4, they will plow in conduit on Uinta from Bear Ln. Aspen Circle. Uinta Dr. will be closed for Bear Ln. to Aspen Circle tomorrow 8/4. Tuesday, they plan to continue along Uinta from Aspen Circle. to Pine Ln. This section of road will be closed on 8/5.
Road base will be placed on Uinta from Lot 44A to Spruce Circle Monday, 8/4. Please avoid this area and use extreme caution.